Türkiye · 2024

Carbon Fibre and Reinforced-Concrete Strengthening — Columns, Slabs and Walls

A reinforced-concrete column wrapped in carbon fibre fabric — CFRP column wrapping
A reinforced-concrete column wrapped in carbon fibre fabric — CFRP column wrapping

In brief

On this project the seismic performance of a building was raised by using reinforced-concrete jacketing and carbon fibre (CFRP) strengthening together. The critical columns were jacketed with a reinforcement cage and new concrete; the remaining columns were wrapped in carbon fibre fabric, carbon laminates were embedded in channels cut into the slab, and the shear wall and wall surfaces were overlaid with carbon fabric.

System
Certified epoxy and carbon system products
Methods
Jacketing + CFRP fabric + carbon laminate
Year built
2024
Areas treated
Columns, slabs, shear walls and walls
Structure type
Reinforced-concrete building (basement and ground floor)
Service line
Carbon Fibre Strengthening

The question asked most often on strengthening projects is this: "should we go for carbon fibre or jacketing?" This project shows that the right answer is usually "both".

The building’s performance assessment showed a serious axial capacity shortfall in some of the columns and inadequate flexural capacity in the slab. Columns with a large shortfall were enlarged by reinforced-concrete jacketing; those with a limited shortfall were wrapped in carbon fibre, and the slab was reinforced with embedded carbon laminate.

The four methods applied

For each member, the method best suited to that member’s need was chosen:

  • Column jacketing — a reinforcement cage was built around the columns with the largest shortfall, formwork erected and new concrete cast.
  • Carbon fibre column wrapping — columns needing ductility and shear capacity were wrapped in CFRP fabric.
  • Slab carbon laminate — parallel channels were cut into the slab, carbon laminate strips were embedded in them with epoxy, and the channels were closed with repair mortar.
  • Wall and shear wall fabric overlay — wall surfaces were overlaid end to end with carbon fabric for in-plane strength.
  • Epoxy injection — existing cracks were filled with low-viscosity epoxy before the fabric was applied.

Why embedded laminate was chosen for the slab

Embedding the carbon laminate in channels cut into the slab, rather than bonding it to the surface, brings two advantages. First, because the laminate sits inside the concrete it takes bond on three faces, so the risk of debonding falls markedly. Second, once the floor finish goes back there is no build-up at the surface — the floor level does not change. The channel depth and spacing were set by the calculation in the strengthening design. In the literature this method is called NSM (near-surface mounted).

Surface preparation: the invisible half of the job

In carbon fibre work, almost every failure traces back to surface preparation. On this site the following steps were carried out in order:

  • Existing render and loose concrete were stripped back to sound concrete.
  • Corroded reinforcement was cleaned and coated with an anti-corrosion primer.
  • Voids and segregation were filled with structural repair mortar.
  • Column corners were rounded so that the fabric would not be cut on a sharp arris.
  • Epoxy primer was applied and surface irregularities levelled with epoxy putty.
  • The fabric was laid in saturating resin and air bubbles rolled out.

Site photographs

20 frames. Tap a photograph to enlarge it.

Existing condition before strengthening — stripped surfaces and shear wall formwork in the basement
The reinforcement cage erected for column jacketing
General site view of the columns with their jacketing reinforcement complete
Columns with reinforcement cages in place, prepared for formwork
Reinforcement layout in the jacketing of columns and shear walls
Formwork and propping arrangement on the jacketed columns
Carbon fibre laminate strips placed in the channels cut into the slab
The site crew applying epoxy adhesive to the carbon laminate strips
Striking off excess epoxy during the slab carbon laminate work
Two workers closing the carbon laminate strips in the slab with epoxy
Completed slab strengthening — the laminate channels closed with repair mortar
General view of the carbon laminate strips running the length of the slab
A reinforced-concrete column wrapped in carbon fibre fabric — CFRP column wrapping
Applying saturating resin with a roller during column wrapping
Carbon fibre fabric overlay on a shear wall, with the scaffold arrangement
The wall surface overlaid end to end with carbon fibre fabric
The texture of the carbon fabric surface after the saturating resin was applied
Repair of a wall crack by epoxy injection, with the carbon overlay around it
Corridor view of the carbon laminate channels cut along the basement slab
Laminate strips and repair mortar in the completed section of the slab strengthening

Frequently asked questions about this project

Can jacketing and carbon fibre be used together in the same building?

Yes, and on most projects that is the most efficient solution. Jacketing is used on members with a large capacity shortfall and carbon fibre on those with a limited one. Both the total cost and the time on site come down compared with resolving everything by a single method.

How is carbon laminate embedded in a slab?

Narrow channels are cut into the slab surface on the axes and at the spacing set by the strengthening design. The channel is cleared of dust, filled with epoxy adhesive, and the carbon laminate strip is pressed into place. The channel is then closed with structural repair mortar. In the literature this method is called NSM (near-surface mounted).

How is it documented that the work was done correctly?

Three records are kept: before-and-after photographs, the batch numbers and declarations of performance of the products used, and the pull-off test results after application. Together those three form the technical file showing that the strengthening was carried out in accordance with the design.

How long does strengthening on this scale take?

It depends on the number of storeys and members. The carbon-fibre-led sections progress in a matter of days, while on jacketed columns the concrete strength gain sets the programme. On this project the two methods were staged and run in parallel, so the waiting periods overlapped.

A similar job

Get a quote for Carbon Fibre Strengthening

Share the dimensions and the current condition; we will price it item by item.

Çobanözü Mah. Toybelen Küçük Sanayi Sitesi, Atakum / Samsun

Our other projects

All projects

Call WhatsApp Request a quote