Samsun · Merkez · 2025
Samsun Piazza Shopping Centre — Waterproofing at Pipe Penetrations
In brief
The waterproofing of Samsun Piazza shopping centre was carried out by Zahan İnşaat in 2025. The work concentrated on the sleeves of the drainage and service pipes passing through the slab; each penetration was filled with a sealing compound and the surrounding area coated with a liquid-applied membrane. Because the centre remained in service, the works were carried out outside trading hours.
- Year
- 2025
- Scope
- Waterproofing at pipe penetrations
- Location
- Samsun Piazza Shopping Centre
- Application
- Sealing compound + liquid-applied membrane
- Structure type
- Shopping centre
- Working pattern
- Centre open, outside trading hours
- Service line
- Waterproofing and Damp Proofing
A leak in a shopping centre is not only a building problem; a closed shop or wetted stock is a direct commercial loss. Waterproofing work therefore has to be quick and conclusive.
On this stage at Samsun Piazza the work was not about broad surfaces but about penetrations. Every drainage and service pipe piercing the slab leaves a void between its sleeve and the concrete; almost the whole of the waterproofing is either solved in those voids or not solved at all.
A leak does not come from the open surface
In waterproofing, failure is almost never in the middle of the coating; it shows up at the details.
- Pipe penetrations — the void between sleeve and concrete is the point most often missed.
- Flanged coupling zones — beneath the fitting is where the membrane loses continuity.
- Wall-to-slab junctions — the lap is left short where the membrane turns up the vertical.
- Around gullies and outlets — where the membrane is not clamped to the flange, water gets underneath.
The sequence at a penetration
The area around the pipe is first cleaned mechanically and loose concrete removed. The void between sleeve and pipe is filled with a sealing compound, dressed to a fillet, and finally the surrounding slab is coated with a liquid-applied membrane so the detail is tied into the surface. Skip that last step and the filler stands alone — it separates at its edge with the first thermal movement.
Site photographs
8 frames. Tap a photograph to enlarge it.
Frequently asked questions about this project
Can waterproofing be done with the shopping centre open?
It can; that is how this project was run. The work is divided into stages outside trading hours, with each stage made ready for use before opening. Setting that pattern up lengthens the programme, but it spares the operator the cost of closing.
Can you find where the leak is coming from?
The hardest part of a leak is finding the source; water may enter metres away from where it appears. During the survey the building details, joints and penetration points are examined, and a controlled water test is carried out if needed. A repair made without identifying the source usually just moves the leak.
Is the waterproofing guaranteed?
We give material and workmanship guarantees. The extent and duration are set out in the contract according to the type of system applied and the condition of the substrate. Sealing solutions at detail points are covered as well.
A similar job
Get a quote for Waterproofing and Damp Proofing
Share the dimensions and the current condition; we will price it item by item.
Çobanözü Mah. Toybelen Küçük Sanayi Sitesi, Atakum / Samsun
Our other projects
Samsun Soho Residences Car Park Floor
A power-floated floor and line marking in a covered car park — a trowelled surface, directional arrows and numbered bays.
Samsun Piazza MV Switchroom Cable Penetration Waterproofing
Cable penetrations letting water into an electrical room: excavation from outside, repair of the wall face, sealing the penetrations and drained backfill.
Osmaniye Düziçi Hacılar Central Mosque
A main dome cast on timber formwork, an in-situ minaret and a muqarnas şerefe straight off the mould — an ongoing project running on formwork we make ourselves.